01
Readiness and design validation
WHAT WE LEADDesign review of the cluster, fabric, power and cooling. Site readiness against the delivery date. Vendor scopes and the interfaces between them.
WHAT YOU GETA validated design and a delivery plan tied to your financing milestones.
CLOSES WITHM1 · Design freezeDesign, bill of materials and schedule agreed.
02
Build leadership
WHAT WE LEADProgram management across vendors and contractors. Installation, cabling and power-on. Daily issue resolution on site.
WHAT YOU GETA delivery program with regular reporting you can share with investors and lenders.
CLOSES WITHM2 · Installed and cabledAll racks installed, cabled to the rail map and powered.
03
Burn-in
WHAT WE LEADFabric bring-up. Sustained stress testing of compute, memory and network. Fault isolation and vendor replacements.
WHAT YOU GETA stable cluster through burn-in, with a record of every fault and fix.
CLOSES WITHM3 · Burn-in completeAgreed thresholds held under sustained load.
05
Workload-ready handover
WHAT WE LEADOnboarding the first production workloads. Runbooks and escalation paths. Handover to your operations team.
WHAT YOU GETA handover pack with runbooks, as-built records and a list of open items.
CLOSES WITHM5 · Production liveFirst production workloads running.